Project Description

Redondo Beach Unified School District – Jefferson Elementary School Retaining Wall Repair

Scope of work included: Demolish existing failed retaining wall and replace it with a 250-foot long retaining wall with a height of 2.5’ to 9.5’ height. Over-excavation and footings required removal and excavation to a depth of 17 feet. Provided all labor, materials, and equipment to perform the scope of work; site protection outside the work area to avoid unintended damage; demolition of existing improvements to accommodate the replacement wall; excavation to accommodate the installation of the retaining wall; forms, reinforcing steel, concrete, and finish of the installed wall; storm drain installation; catch basin; restoration of the site to post-construction activities to provide a complete and functional poured-in-place retaining wall and related site improvements. Fred Naile, Director of Facilities – (310) 901-8947.